9th of September 2024, 12:00am to 21st of January 2025, 6:00am

UPDATE 13/01/25): Due to changes in the programme of works, surfacing on the A9 Spey River Bridge will now be completed on Tuesday 21 January 2025.

BEAR Scotland, on behalf of Transport Scotland, are set to carry out essential maintenance work on the A9 Spey River Bridge near Kingussie.

The works will involve concrete repairs, replacing the bridgedeck waterproofing, resurfacing the road and installing new expansion joints. These works are being carried out to prevent defects in the road surfacing caused by failure of the underlying bridge waterproofing.

These maintenance works start on Monday 9 September and will be completed by Friday 20 December.

To ensure the safety of both road users and the workforce, this single carriageway section of the A9 will be reduced to one lane over the bridge. Two-way temporary traffic lights will be in place 24 hours a day for the full duration of the works. For some overnight works, a convoy traffic management system will be required to safely escort road users through the site.

 

Ian Stewart, BEAR Scotland’s North West Representative, said, “These essential works on the Spey River Bridge will deal with on-going problems with the existing road surface on the bridge.”

“We will do everything possible to complete this essential maintenance as quickly and safely as possible. We thank all road users and the local community for their patience in advance.

“Please plan ahead by checking the Traffic Scotland website for up to date journey information and leave some extra time to complete journeys.”

Real time journey information is available from Traffic Scotland on www.traffic.gov.scot, X @trafficscotland or on the mobile site my.trafficscotland.org.

UPDATE (06/01/25): Unfortunately, surfacing on the northbound verge areas of the bridge deck was unable to be completed on the A9 Spey River Bridge due to poor weather conditions. Operatives will return for one night on Monday 20 January 2025 to complete the work under temporary traffic lights.