M74 Nethan Viaduct | Bridge Refurbishment
Amey, on behalf of Transport Scotland, is undertaking major bridge refurbishment works on the M74 at Nethan Viaduct, south of Junction 10. The 30-week programme of improvements will take place in five phases and includes waterproofing, concrete repairs, resurfacing, expansion joint replacements, edge beam strengthening, and barrier upgrades. The programme of refurbishments will run from Tuesday 1st October 2024 until Thursday 26th June 2025 under a 2+2 contraflow system.
This scheme will benefit vehicles using this route each day, by improving the safety and condition of the carriageway and the associated structure.
Average speed cameras, installed between Junctions 9 and 11, will be in operation throughout the duration of this project with traffic speed reduced from 70mph to 30mph. This 30mph restriction is necessary to ensure the safety of personnel and members of the public given the use of narrow lanes to permit 2 lane flows to be maintained, whilst also considering the high volume of HGV traffic on this route.
M74 Northbound
Phase One: From Tuesday 1st October until Sunday 2nd February 2025 a 24-hour northbound hard shoulder and Lane One closure of the M74 carriageway will be in place. 2 lanes in both directions will remain open throughout the works. However, this will switch to 1 lane open in each direction from Friday 6th December until Friday 20th December 2024 to accommodate carriageway resurfacing works on the M74 at Junction 11. Full details of which are available here.
Phase Two: From Monday 3rd February until Sunday 16th February 2025 a 24-hour northbound Lane One and Lane Two closure of the M74 carriageway will be in place. 2 lanes in both directions will remain open throughout the works.
Abnormal loads will be restricted on the northbound carriageway at this location during the above dates due to insufficient lane widths. Southbound carriageway access will be unaffected during this period.
An overnight total closure is required at the beginning and end of each phase.
M74 Southbound
Phase Three: From Monday 17th February until Tuesday 20th May 2025 a 24-hour southbound hard shoulder and Lane One closure of the M74 carriageway will be in place. 2 lanes in both directions will remain open throughout the works.
Phase Four: From Wednesday 21st May until Tuesday 3rd June 2025 a 24-hour southbound Lane One and Lane Two closure of the M74 carriageway will be in place. 2 lanes will remain open throughout the works.
Abnormal loads will be restricted on the southbound carriageway at this location during the above dates due to insufficient lane widths. Northbound carriageway access will be unaffected during this period.
An overnight total closure is required at the beginning and end of each phase.
M74 Central Reserve
Phase Five: From Wednesday 4th June until Thursday 26th June 2025 a 24-hour Lane Two closure on both the northbound and southbound M74 carriageway will be in place.
Access for emergency service vehicles will be maintained throughout these works.
Please note, all schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.
How to get the latest travel and traffic information
For full information on roadworks on trunk roads in the south-west of Scotland, visit the Amey website.
You can report a defect on the network by filling out this form.
Follow Amey South West Trunk Roads on Twitter at @SWTrunkRoads.